• Technical

    • Appointment: 1997
    • Construction Start: 1999
    • Completion: 2000
    • Area: 100,000ft²
    • Budget: £48million
    • Form of Contract: Traditional
    • Client: Ogilvy & Mather Advertising Agency
    • Services Engineer: Whitby Bird
    • Structural Engineer: Whitby Bird

A deep plan (two 5,300 m² football pitch-sized floor plates) and the adhoc hard-to-navigate layout that had emerged over 10 years meant staff were less inclined to leave their desk & collaborate. After 3 months a brief was developed which suggested a switch from departmental to client-focused teams. Connectivity would be key. Two 250m² voids were cut between the floors. Construction was carried out in occupation in five phases of 2-3 months.

  • Technical

    • Appointment: 1997
    • Construction Start: 1999
    • Completion: 2000
    • Area: 100,000ft²
    • Budget: £48million
    • Form of Contract: Traditional
    • Client: Ogilvy & Mather Advertising Agency
    • Services Engineer: Whitby Bird
    • Structural Engineer: Whitby Bird